This is a tentative schedule, and could change as we go along. We will keep this page updated as we move along in the process.
***Be sure that your files have been saved off of your computer and your GroupWise archive directory is pointing to the s:\gw\archive folder and they work as expected. This should be completed no later than May 11, 20012****
May 2012
7 Consultant comes on Campus for back-end setup
14 Maintenance (5) and Director IS (2) **Done**
15 IT Services **Done**
16 Institutional Effectiveness and Copy Center (15) **Done**
17 hire date for temp workers and Training
21 Personnel (10) **Done**
22 Shipping (5) , **Done**
23 Business Office (60) , **Done**
28 Memorial Day
29 Student Services including Q-bldg (65) **Done**
31 Instructional Services (14) **Done**
June 2012
4 Begin LRC (30) **Done**
8 DataNetworks complete (consultant no longer on campus)
11 Learning Lab (20) **Done**
12 9-Month Faculty Begin
14 Continuing Education C, T, X, and Basic Skills (1st floor S-bldg.) (60) **Done**
18 Begin Instruction
Deans and Departments by Buildings 6th floor S-Bldg. and on down
S, A, N, W, L, K, R, F, E, V, NA, NB, NC, ND, NY, NZ
19 PSTC bldg, and Social & Behavioral Science
20
July 2012
24 **All Faculty and Staff Workstations are Done**
27 Begin Lecture Classroom Computers, but not the computer labs.